Please see the photos and associated project update summary below.  I think the mall area surrounding Burrowes building was dressed up nicely for commencement this weekend and we received a lot of positive feedback about the project.  The overall schedule remains on track and it'll be a busy summer with all the utility work across the mall area starting shortly.

 

If you have any project specific questions, please let me know.  Thanks, Chris

 

Overall Progress:

  • South Wing 4th & 3rd floor demolition & abatement complete
  • Core Building 3rd floor abatement & demolition complete
  • Window removal has begun on the top floor
  • South Wing 2nd floor demolition complete and abatement in progress
  • Core Building 2nd floor abatement complete and demolition is in progress
  • North Knuckle demolition is in progress
  • Basement excavation is in progress

Upcoming Work:

  • Abatement and demolition will continue down thru the building
  • Shoring added to basement for new foundation work
  • MEP hanger rough-in starting on upper floors
  • Site utility work will start in the Pattee Mall area