January 5, 2015: Burrowes Project Update

You are here: Home / About / New Facilities / Burrowes Renovation Project / Project News Archive / January 5, 2015: Burrowes Project Update

From: Susan Welch
Subject: Burrowes project update -- January 5, 2015

To those interested in the Burrowes building project:

Welcome back.  I hope your holiday was a pleasant and productive one.

Work continued on Burrowes over the holiday.  Chris Hort has summarized progress below, accompanied by photos.

From Chris:  At this halfway point, the project schedule remains on track and the framing and drywall work in the wings is in full swing working from top to bottom. Four mock-up rooms were completed in the North wing, including accent wall colors, to support the set up of office furnishing options by vendors for our review. The shoring and foundation related work occurring in the knuckles will be followed by construction in these areas starting around the end of January.

If you have any project specific questions, please let me know.
Thanks. Chris

Overall Progress:

  • North Wing mock-up rooms complete
  • North knuckle shoring continues
  • South knuckle underpinning complete
  • Core basement equipment pads poured
  • Drywall continues in upper floors of wings
  • Door frame installation on the top floors of wings
  • Sidewalk complete near Chandlee Lab
  • Temporary heating installed in core

 

    Upcoming Work:

    • Final masonry mock-up to be built
    • Framing continues
    • Install temporary heating in wings
    • Drywall installation on top floors in wings continues
    • Needle beams to be installed into North knuckle foundation

     

    North knuckle shoring continues

     

    North Wing mock-up rooms complete - room 138 mock

     

    Sidewalk complete near Chandlee Lab

     

    South Wing - 3rd floor door frames and drywall

     

    Temporary heating installed in core

     

    Core basement equipment pads poured